Construction Stage 4 – Fixing

Fixing follows on from Lock Up.

The fixing stage is moving from a very rough looking interior to something resembling the house you are expecting.

During this stage the following works will be taking place:

  • Install Insulation This includes both roof and wall insulation Although the wall insulation will be installed before dry walling the ceiling insulation may be installed following ceiling board installation.
  • Plasterboard installation This will include ceiling boards, wall boards and cornices.
  • Air conditioning / Ducted Heating If a large main unit is mounted in the roof space it may be installed before the ceiling boards are in place. The ductwork will follow ceiling installation.
  • Waterproofing Wet Areas This is applied to floors and walls before tiling
  • Carpentry – First Fix This sees the kitchen cupboards and bathroom vanities installed. Doors, drawers, and counter tops are often left off at this stage. Skirting boards and architraves and internal window sills are also installed.
  • Main Plumbing Fixtures Baths, basins, sinks shower trays and laundry troughs are installed and connected to the drainage system. Taps, mixers and toilet bowls are usually left off until after tiling.
  • Tiling Both wall and floor tiling are normally completed at this stage.
  • Portico and Carports These will be constructed at this stage together with any freestanding garage. It’s likely that the garage door however will be left until later.

The Practical Completion Inspection (PCI) will be coming up soon. This PCI Guide tells you what you need to look out for.

Where you surprised by anything about your house when you visited during the construction phase?

 

For similar posts see Construction Stages

For more on stage payments see Progress Payments

 

facebooktwittergoogle_plusredditpinterestlinkedinmailby feather
WAS THIS INTERESTING? . . . . WHY NOT BUY anewhouse GUIDE ONLY $4

2 comments to Construction Stage 4 – Fixing